فيصلو 02/2023 - مائونٽ براون لاءِ پري پلاننگ جو معاهدو

ليکڪ ۽ نوڪري جو ڪردار: ايليسن بولٽن، چيف ايگزيڪيوٽو

حفاظتي نشان: سرڪاري

ايگزيڪيوٽو خلاصو

The Commissioner is asked to sign a pre-planning agreement with Guildford Borough Council, relating to the Mount Browne Police HQ in Guildford and proposed plans for its re-development.

A Pre-Planning Agreement (PPA) is an agreement between the developer (the PCC) and the Planning Authority (Guildford Borough Council).  It provides a project management framework for handling the pre-application period, prior to the submission of a planning application.  It is designed to speed up the pre-planning process by committing both parties to an agreed timetable and making clear what level of resources and actions are required to ensure all key planning issues are properly considered.  It does not give any guarantee that Guildford BC will grant planning permission for the development and relates solely to the process of considering development proposals, not the decision itself.

The agreement comes at a cost to the developer to cover costs associated with work up to submission of an application.  It has been reviewed by Surrey Police’s Programme Director, Maureen Cherry and by Vail Williams on behalf of the PCC.

تجويز

To sign the Pre-Planning Agreement with Guildford Borough Council as relates to the redevelopment proposals for Mount Browne HQ.

پوليس ۽ ڪرائم ڪمشنر جي منظوري

مان سفارش (سفارشون) کي منظور ڪريان ٿو:

دستاويز: ليزا ٽائونسينڊ، سري لاءِ پوليس ۽ ڏوهن جي ڪمشنر (پي سي سي آفيس ۾ ٿيل گلي جي دستخط ٿيل ڪاپي)

تاريخ: 17 اپريل 2023

سڀ فيصلا فيصلا رجسٽر ۾ شامل ڪيا وڃن.

غور جي علائقن

مشاورت

Surrey Police Programme Director; Vail Williams.

مالي اثر

Fees of £28k to Guildford BC for support during the pre-planning process. 

ي

The PPA is made pursuant to Section 111 of the Local Government Act 1972, Section 2 of the Local Government Act 2000, s93 Local Government Act 2003 and s1 Localism Act 2011

مول

ڪو به پيدا نه ٿيو.

مساوات ۽ تنوع

No issues arising.